Commercial refurbishment programme
Drylining an occupied office: the work sequence
Plan from a usable room backwards: surveys, service changes, inspections, boarding, decoration and handback each need a place in the programme.

Drylining can sometimes be phased within an occupied office, but the programme has to separate the work from the people using the premises. Decide which rooms can close, which activities must move and what services need interruption before booking the installation. A fast boarding stage is little help if the electrician cannot reach the wall, finishing materials are still drying or the room is waiting for its lighting to be tested. Agree the whole return-to-use sequence.
Start with the room’s handback requirements
Write down what the business needs in order to use the space again. That may include a closed and decorated partition, functioning doors, power, data, lighting and ventilation, furniture in position and clear access. Assign each item to a package. The drylining contractor may supply some of them, while others remain with the fit-out contractor or separate trades.
Agree the acceptance checks and the person who coordinates them. A wall can be complete to the drylining scope while its room is still unavailable because another package has unfinished work. Show both milestones in the programme so that “boarding complete” is not mistaken for a date on which staff can return.
Include the decisions needed before either milestone is achievable: room layout, wall construction, doors, fixture positions and finishes. Late changes to these can reopen work already finished. Identify who can authorise a change and how its effect on other trades and room availability will be recorded.
Survey before confirming the closure period
Inspect the floor, ceiling and adjoining walls along the proposed work. Establish the intended partition height and support, including the space above a suspended ceiling where relevant. Record retained fittings and the service routes that the alteration crosses. A measured plan alone will not show every condition behind a lining or above a tile.
For commercial premises built or refurbished before 2000, check the asbestos information against the areas the work will disturb. HSE’s refurbishment survey guidance includes affected hidden fabric. An existing management survey may leave those areas uninspected. Arrange the appropriate investigation and any necessary follow-on work before the strip-out programme is treated as settled.
Some inspection can require temporary access or an opening that then needs reinstatement. Agree those visits separately where necessary. The resulting information should resolve the installation method or identify a defined outstanding item, rather than leaving the first installation day to become an unplanned investigation.

Allocate the client and coordination responsibilities
An office fit-out commissioned by a business falls within HSE’s commercial-client guidance for the Construction (Design and Management) Regulations 2015. The client needs suitable arrangements, time and resources for managing the project, together with relevant information about the premises. These duties are not confined to large developments.
Where more than one contractor will work on the project, or this is reasonably foreseeable, the client must appoint a principal designer and principal contractor in writing under CDM2015. Make those appointments as soon as practicable and before construction begins. The largest drylining package does not automatically make its installer responsible for coordinating the whole refurbishment.
Provide the operational constraints to that team: people remaining in the building, restricted routes, delivery access, sensitive equipment and necessary shutdowns. The project arrangements can then address them alongside the construction work. If continued occupation cannot be managed suitably during a particular operation, build an alternative into the plan instead of treating uninterrupted use as a promise.
Set up the work area before removing the old layout
Define the boundary of the work area, its access and how it will remain separated from the office. Coordinate retained circulation and escape arrangements with the people responsible for the premises and project. A future permanent partition cannot provide a boundary while it is still incomplete, so any temporary arrangement needs its own planning.
Agree which furniture and equipment will be removed, who moves it and where it goes. Keeping everything beside the proposed wall can prevent preparation, delivery and inspection. Check the route for full sheets and long framing members as well as the final storage area. A new wall may close a route that later materials would otherwise need.
Arrange service isolation and removal through the appropriate trades before stripping affected construction. Identify what can remain operating elsewhere and which interruptions require notice to users. Keep temporary services and work-area arrangements under coordinated control as the layout changes.
Scroll sideways to see the full table. Keyboard: focus the table, then use the arrow keys.
| Stage | Information needed before moving on |
|---|---|
| Survey and design | Affected fabric, selected construction and resolved service routes |
| Work-area setup | Agreed separation, access and operational arrangements |
| Framing and first fix | Supports, openings, backing and service positions |
| Concealed inspection | Specified components and treatments checked before closure |
| Finish and decoration | Selected materials ready for the next stage |
| Room handback | Assigned checks, services, access and outstanding items recorded |
Coordinate framing, first fix and the closure inspection
Once the room is set out, check the finished wall faces and openings against the accepted layout. Allow for all board and finish layers, not just the frame centreline. Doors, socket positions and fitted equipment need to work against the completed surface, so resolve a conflict before it becomes concealed.
Install the specified backing and coordinate first-fix services while access remains available. The partition and service trades need an agreed order for their work and the associated opening treatments. A service crossing can affect the wall’s fire or acoustic construction; include the required compatible detail and responsibility for it.
Place an inspection point before closure. Check the selected framing, supports, cavity components, service interfaces and any movement detail that will be hidden. Record the findings and resolve incomplete items before the next board layer or adjoining ceiling removes access. Photographs can supplement that record, provided they identify the actual wall and stage clearly.
Allow finishing to follow its material sequence
Taping, filling, drying, preparation and decoration are separate operations. Follow the selected products’ instructions and the site conditions they require. A compound that has set may still need to dry before the following finish. The programme should accommodate the specified stages instead of assuming that a wall is ready for paint as soon as its joints feel firm.
Agree the intended decoration and relevant lighting before accepting the surface. Strong side lighting can make uneven joint treatment more apparent. Inspect under conditions that relate to the finished room and resolve the work within its agreed scope, rather than leaving a general “ready to paint” label for the decorator to interpret.
Protect completed faces from remaining installation work. Door fitting, final electrical accessories and equipment mounting can all affect a freshly decorated surface. Coordinate their order and assign making good where it is needed. A room that has been repainted twice because the sequence was unresolved has gained little from an early boarding date.

Return the room through a coordinated final check
Walk through the room against the agreed handback list. Check the visible finish and junctions, the doors and planned access points, then confirm that relevant service testing or commissioning has been completed by the responsible trades. Record outstanding items individually with an owner and completion arrangement.
Keep the wall-system references, concealed support locations and accepted alterations with the premises records. They will help when the business later moves a screen, adds a socket or changes the room again. Include maintenance or access information provided for components within the work.
For phased projects, apply the same handback process to each room or work zone. Review what the next phase needs before moving its boundary or storage. The useful completion measure is a room that meets the agreed conditions for return to use, with the required records and any remaining work understood by the business.
Questions and answers
Can staff keep working beside the refurbishment?
Sometimes. Assess the actual work, separation, access, services and operational risks with the project team. Certain operations may require a room or larger area to close; agree those periods before committing to the programme.
How long will the drylining take?
The layout, selected wall system, services, finishing and drying stages, and phased access determine the duration. Ask for a programme covering survey and strip-out through framing, inspection, boarding and finishing, including the separate work needed for handback. Room dimensions alone do not fix that timetable.
Sources and further reading
- HSE: Commercial clients—roles and responsibilities under CDM2015Source checked: 31 October 2026
- HSE: Find out if asbestos could be present in your buildingSource checked: 31 October 2026
- FIS: Drylining technical guidanceSource checked: 31 October 2026
- British Gypsum system principles: partition interfaces, height and fire behaviourRelease/version: Relevant sections: 11 September 2023Source checked: 30 October 2026
- British Gypsum Finishes: jointingRelease/version: Jointing section: 13 November 2025Source checked: 30 October 2026
- Construction (Design and Management) Regulations 2015, regulation 5: principal appointmentsSource checked: 31 October 2026